ALSTOM

ALSTOM A62-0125 Relay

Importing Slave Configuration Files (.GSD)

GSD Files and Bitmaps can be imported by selecting FILE then Copy GSD whilst in the

network configuration window

Module Installation

The Fieldbus Modules are peripherals of the TCP/IP Ethernet module (9716-4020).

Prior to the installation of any Fieldbus modules, ensure that a TCP/IP Ethernet module

is correctly installed and configured. Refer to the GEM80-500 Series Controller

Technical Manual for installation instructions and the GEMLAN-T Technical Manual for

configuration instructions for the TCP/IP Ethernet module.

VEGA MET 602 Ex
Saab SCB5110 9240 021-203
GE IS200WROBH1A
TRICONEC 3603T
TRICON 4355X
Triconex 4000189-530
ABB PFVL142(16MM)
ABB AT868-2-1-1
ABB FVL141V-16MN
Meggitt IOC-CARD FOR MPC4
200-560-0001HH
GE DS200TCDAH1B
GE DS200TCPSG1A
Yokogawa S2CP471-01 S2CP471-01
Prosoft MVI56-PDPS
GE DS200TCDAH1B

Before installation, the Fieldbus module must be hardware configured by setting the

Module Identification rotary switch. Refer to section 4.3.

With the controller powered down remove the front panel mains and watchdog

connector. Move the controller to a suitable location and proceed as follows, noting

that all references to left and right refer to the controller when viewed from the front.

(a) Release the upper right-hand side cover and power supply assembly. Lay the

controller down on its left-hand side and remove the four M3 Pozi-pan head

earthing/grounding screws. Retain for re-assembly.

(b) Lift the cover and slide the louvered side under the controller.

(c) The TCP/IP Ethernet module should now be visible. This is retained using four M3 x

6 mm screws and spring washers. Remove these screws and washers and retain for

re-assembly.

(d) Secure the TCP/IP Ethernet module in position by substituting 4 mounting pillars for

the M3 x 6mm screws.

(e) The site is now ready to receive a Fieldbus module.

(f) Check that the connector pins on the underside of the Fieldbus module are correctly

aligned. Orientate the module so that the matching connectors are in line. Gently

push the connector halves together until the module sits flat on the mounting

pillars.

(g) Insert the front panel mounted Fieldbus and diagnostic ribbon cables to their

associated headers.

(h) Secure the Fieldbus module in position using 4 more mounting pillars.

If all required Fieldbus modules are now fitted proceed at instruction (j), otherwise

continue at instruction (e).

The site is now ready to receive the power converter module.